The Fosterville Gold Mine is the highest gold producing mine in Victoria. In 2017, EMtek was engaged to support the pending work schedule at the Fosterville Gold Mine for Agnico Eagle. EMtek provided project management, administration, engineering and design service and construction coordination requirements to support the pending workload. EMtek’s personnel were utilised both on and off site for the entire project duration. EMtek constructed a project team to assist Kirkland Gold to successfully implement their project portfolio.